Hot Work Safety

Hot Work (Welding, Cutting and Brazing)

Hot work operations use an open flame or generate sparks, such as cutting, welding, brazing, soldering, grinding, thermal spraying, thawing pipe, and installation of torch-applied roof systems. The majority of indoor campus hot work takes place in EHS approved designated locations. If you are performing hot work in an undesignated location, you must apply for a hot work permit using the Facilities Management Archibus Work Order System.

What you need to know

The University has developed a Hot Work program to comply with the Occupational Safety and Health Administration (OSHA) regulations. The program requires the following:

  • The designated hot work locations are approved and marked with signage
  • Hot work permits must be submitted for any hot work in an undesignated location
  • Hot work permits must be authorized prior to work starting
  • Hot work operators must be designated, authorized, and deemed qualified by their supervisor
  • A fire watch must be designated, trained in fire extinguisher use, and remain 30 minutes after hot work operation
  • UV shielding should be provided for arc welding
  • Personal Protective Equipment (PPE) listed in the equipment owner’s manual must be worn during hot work operation
  • The hot work area and equipment must be inspected

Services

The Environmental Health and Safety Office offers the following services:

  • Consultative regulatory review
  • Hot work permit authorization
  • Signage
  • Limited equipment testing
  • Inspections
  • Training

Resources